CCMA – Town Creek Lift Station and Force Main

Contract amount: $3.3 million The scope of Work: Installation of 12,500 LF of 24″ force main and rehabilitation of existing lift station to include, replacing pumps, piping, electrical gear, and overhead hoist system. Ancillary scope included coordination and tie-in to existing WWTP head works, directional bore through an environmentally sensitive area and installation of (2)…

Learn More

Highland Estates Montana Pass

Contract amount: $5.8 million Built 2.5 million gallon ground storage tank, installed 5 vertical turbine pumps with associated steel piping. Installed Hydropneumatic tank, as well as a pressure sustaining valve and performed all site work.

Learn More

Project D Distillery

Contract amount: $29 million The general contractor for the expansion of distillery. Constructed four distilling buildings, 22,000 sf each; 166, 000 sf bottling building, warehouses, detention ponds, channel excavation, erosion control on 32-acre site. Self-performed complete civil package including mass excavation, site utilities, storm drainage, lift stations, and concrete retaining walls

Learn More